Highway Maintenance on Nicosia-Limassol and Paphos-Limassol Routes

highway maintenance ongoing construction

The ongoing highway maintenance on the Nicosia-Limassol and Paphos-Limassol routes in Cyprus will continue until February 29th and March 21st respectively. Lane closures and traffic management measures are in place, and drivers are advised to follow posted signs and reduced speed limits for their safety and the safety of construction workers.

What are the current highway maintenance schedules for Nicosia-Limassol and Paphos-Limassol routes?

  • Nicosia-Limassol: Maintenance including safety barrier repairs and installation of reflective studs takes place from 9:00 pm to 5:00 am, Monday through Thursday, until February 29th.
  • Paphos-Limassol: Road surface work is scheduled from 8:00 pm to 5:30 am, excluding Fridays to Sundays, and is expected to be complete by March 21st.

Ongoing Construction and Road Closures

The ongoing construction on the Nicosia-Limassol and Paphos-Limassol highways in Cyprus is set to continue through tonight, impacting travel for many. Drivers are urged by the Police to remain vigilant during this time and adhere to posted signs and reduced speed limits.

Nicosia-Limassol Highway Work Schedule and Details

Current Lane Closures and Traffic Management

On the Nicosia-Limassol highway, work is being conducted from Akti Kiverniti to Germasogeia. To facilitate this, lane closures are being implemented in stages. While work is underway, one lane will be closed, and vehicles will be redirected to the adjacent lane, as indicated by traffic signs.

Timings and Nature of Work

The maintenance work—including safety barrier repairs and the installation of reflective studs—is being carried out during quieter hours to minimize disruption. This schedule runs from 9:00 pm to 5:00 am, Monday through Thursday. The project commenced on January 10th and is projected to conclude by February 29th.

Paphos-Limassol Highway Maintenance Activities

Impact on Traffic and Detours

Similarly, on the Paphos-Limassol highway, both lanes and directions towards Paphos and Limassol will experience maintenance work tonight. During this period, traffic will be rerouted through alternative highway exits to enable the road surface maintenance work.

Work Schedule and Completion

The work here is scheduled from 8:00 pm until 5:30 am, omitting Fridays, Saturdays, and Sundays. Starting from January 29th, this segment of the maintenance is expected to be finished by March 21st.

Safety Measures and Police Advisory

To ensure the well-being of all, the Police have issued an advisory for drivers traveling through the affected areas:

  • Maintain a reduced and safe speed
  • Keep a safe following distance from the vehicle ahead
  • Follow the temporary road signs and signals

By staying alert and compliant with these guidelines, motorists can help ensure safety for themselves and the construction workers on site. The completion of these important maintenance projects will ultimately lead to safer and more efficient travel on these critical transportation routes.

Highway maintenance is currently taking place on two routes in Cyprus: Nicosia-Limassol and Paphos-Limassol. It involves repairing safety barriers, installing reflective studs, and working on the road surface. The maintenance work is happening during certain hours to minimize disruption, and lane closures and traffic management measures are in place. Drivers are advised to follow the signs and reduced speed limits for their safety and the safety of the construction workers. The work on the Nicosia-Limassol route will continue until February 29th, while the work on the Paphos-Limassol route is expected to be completed by March 21st. The police have issued an advisory for drivers to maintain a reduced speed, keep a safe distance from other vehicles, and follow the temporary road signs and signals. The completion of these maintenance projects will lead to safer and more efficient travel on these highways.

About The Author

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top